FTC Solar's Q3 2026 disclosure described two Indian contracts: 118 MW with Tata Power Solar in Gadag, Karnataka, and 121 MW with Evren in Andhra Pradesh.
The two awards are often quoted as a single 239 MW India entry. They differ in counterparty, state, production status and expected delivery timing.
A project database needs to hold those differences rather than a single total.

Project scope
Field-by-field comparison
Owner, state, capacity, production start and delivery status are recorded separately. One project is described as having started production; the other is expected to be operational before Q1 2027.
Why this project is a useful reference
State machine language
Signed contract, production started and planned commissioning are three different states. Our record keeps the original wording for each.
Local-content context
Indian procurement rules and ALMM-style requirements influence which tracker suppliers can serve a project. We note the policy context without attributing the awards to it.
Data box
| Field | Value as reported |
|---|---|
| Tata Power Solar | 118 MW, Gadag, Karnataka, production started |
| Evren | 121 MW, Andhra Pradesh, Brookfield-backed, before Q1 2027 |
| Combined | 239 MW |
| Disclosure | FTC Solar Q3 2026, 4 November 2026 |
| Backlog context | About USD 640 million |
All figures above are quoted with the unit and reference period used by the primary source. They are reproduced here for reference, not independently re-measured.
What is not confirmed: verification note
Both contracts were won after the Q3 period closed. They are post-period awards and are not included in Q3 revenue.
What to watch next
Commissioning notices and any revision to the stated backlog.
Primary sources
- FTC Solar Q3 2026 results / Form 8-K, 2026-11-04
- Tata Power Solar disclosures
- Evren / Brookfield platform disclosures
Researched and written by the solarrack.wiki editorial desk. Every figure in this article carries a source and a verification note; where a claim could not be confirmed against a primary document, it is labelled as such. Corrections: [email protected]